Bridge and construction method of bridge

其他/未提供未知

数据来源:EPO OPS

正文暂时无法获取,您仍可查看已取得的基本信息。

92777719专利族
§ Ⅰ

卷宗概要

申请人

BYD CO LTD

申请号

CN202310304573

发明人

ZUO XUENA; RUAN HUIQIANG

申请日

Mar 21, 2023

公开日

Sep 24, 2024

专利族 ID

92777719

IPC 分类

E01D19/02E01D19/12E01D21/00

CPC 分类

E01D19/02E01D19/12E01D21/00

The invention discloses a bridge and a bridge construction method. The bridge comprises a track beam; the bridge pier assembly is arranged below the track beam, the bridge pier assembly comprises a bridge foundation and a bridge pier, the bridge foundation is arranged below the bridge pier, the bridge foundation comprises a first concrete part, a plurality of first main reinforcements, a plurality of second main reinforcements and a first sleeving piece, the first main reinforcements are arranged at intervals in the length direction, and the second main reinforcements are arranged at intervals in the width direction; the plurality of first sleeving pieces are arranged at intervals in the width direction; and the first sleeving piece is connected to the outer side of the second main reinforcement in a sleeving mode, the second main reinforcement can move relative to the first sleeving piece, and the first concrete part wraps part of the first main reinforcement and the first sleeving piece. The movable space is reserved through the first sleeving piece, so that in the connection construction of the track beam and the pier, more movable space is provided for the second main reinforcement through the first sleeving piece, other additional operations such as engineering rework or reinforcement planting caused by mutual conflict of the reinforcements can be avoided, and the construction period is prevented from being delayed.

EPO 研究资料

选择栏目后,按需获取当前文献的官方资料。

选择上方栏目查看对应资料。

专利研究工具